Critical path method
A. helps in ascertaining time schedules
B. makes better and detailed planning possible
C. provides a standard method for communicating project plans schedules and to time and cost performance
D. all of the above
Answer D
In a functional organisation
A. quality of work is better
B. wastage of material is minimum
C. specialised knowledge and guidance to individual worker is provided
Break even analysis is
A. short term analysis
B. long term analysis
C. average of short and long term analysis
D. any of the above
Answer A
A critical activity has
A. maximum slack
B. minimum slack
C. zero slack
D. average slack
Answer C
Gantt chart is used for
A. inventory control
B. material handling
C. production schedule
D. machine repair schedules